Home > News and events > The Noyon quay works are complete
The work on the Noyon quayside has been completed with a rather unusual step: waterproofing the quayside by spraying concrete... underwater.
To recreate a seal at the bottom of the Canal du Nord and stabilize the banks, riprap is carefully placed using a shovel equipped with a clamp. The whole is percolated by a colloidal concrete* type applied with a pump positioned on the platform of the quay.
A diver works underwater to guide the hose during the concrete spraying process, while another takes measurements to ensure the concrete is properly distributed. Watch this process in pictures!
* Colloidal concrete is a type of concrete that can be poured underwater and is cohesive and homogeneous.
Want to learn more about the construction stages of the quay? Check out the news dedicated to the 5 quay works in the Oise region, which lists the implementation stages.