Home > News and events > Start of civil engineering work on the Montmacq lock – Cambronne-lès-Ribécourt
If you've been following the construction progress, you're familiar with the initial stages of work on the Montmacq – Cambronne-lès-Ribécourt lock, which have already been completed: the diaphragm walls and the excavation of the lock chamber . Since then, excavation of the downstream and upstream lock heads has begun, as well as the civil engineering work on the lock chamber itself. What exactly does civil engineering entail? What work is currently underway? We'll explain below.
The first stage of the lock construction involved creating a watertight enclosure using diaphragm walls poured to a depth of 20 meters . Once these walls were completed, dry excavation of the structure became possible thanks to a groundwater lowering system . Carried out in several phases, this system, once the structure was excavated to a depth of 12 meters , allowed for the construction of the lock floor, known as the invert, as well as the final walls , called the lock walls . These are the stages currently underway in the lock chamber.
The civil engineering phase* of the lock began at the end of April 2026. The lock floor and its walls are being constructed gradually, in several stages. Initially, steel reinforcements are installed and secured together . Then, the concrete slab is poured section by section using concrete pumps.
Once the foundation slab is finished, the construction of the lock walls can begin. This is done in two stages, the "lifts", the first of which begins in May 2026.
The first lift is completed to a height of just over 3 meters because the struts, installed during the excavation of the lock chamber, are still in place to support the diaphragm walls. They will be removed before the construction of the second lift , later this summer, which will rise to just over 9 meters , reaching the top of the lock chamber.
The lock walls are constructed using "lost" formwork which is integrated into the structure and therefore remains in place once the concrete has been poured. They will be 2 meters thick, just like the lock's foundation slab.
*Civil engineering includes all the operations involved in constructing a structure (bridge or, as in this case, a lock).
Since April 17, 2026, a viewing platform, installed near the construction site, allows visitors to discover the progress of the construction in complete safety.
Accessible from the towpath in Thourotte, after crossing the bridge over the Oise lateral canal, it allows you to observe the ongoing work and discover the major stages of the work thanks to information panels.