Home > News and events > The State authorizes railway restoration work
The environmental permits for the work to be carried out by SNCF Réseau on two railway lines, upstream of the Seine-Nord Europe Canal project, have been signed by the Prefect of the Oise and the Prefect of the Somme. These decisions mark a decisive step towards the operational launch of the railway construction projects, which will adapt and modernize existing infrastructure in the area served by the future waterway.
The environmental permits issued by the State confirm the project's compliance with regulatory requirements regarding impacts on wildlife and vegetation, water management, nuisance prevention, and ecological compensation. They now allow SNCF Réseau to schedule the start of the initial works, planned for this year and expected to last nearly three years.
Fully mobilized alongside the Société du Canal Seine-Nord Europe (SCSNE) and institutional partners, SNCF Réseau is contributing to a project that will promote modal shift, the ecological transition of freight transport and the economic competitiveness of the territory.
The applications for environmental authorization (DAE) for the railway restoration of the Creil-Jeumont line (Paris-Saint-Quentin line) and the Amiens-Laon line were submitted to the relevant government departments in 2023. These applications detail the environmental measures related to the railway works. After several years of discussions with the permitting authorities, consultations with relevant organizations, and following the favorable opinion issued by each of the public inquiry commissions held in the fall of 2025, the prefects of the Oise and Somme departments each signed the environmental authorization order for the planned works (see below).
Therefore, nearly 80 hectares of specific environmental improvements will be implemented:
[1] The tall-herb community or wet wasteland is a heterogeneous grassland plant formation consisting of tall grasses, developing on rich and wet soils.
[1] The principle of constructing a viaduct that spans the Ingon valley for the new line greatly limits environmental impacts.
The management of these compensation sites for the Seine-Nord Europe Canal, once completed and operational, is entrusted for 30 years to specialized organizations, and is financed by the SCSNE.
The work is being carried out by SNCF Réseau, which is the project owner. The work consists of:
For the works to restore the Creil-Jeumont railway line, which will connect Paris, Noyon and Saint-Quentin by train:
For the work to restore the Amiens-Laon railway line :
Added February 9, 2026 - Updated February 9, 2026