Meeting with the Mayors of Cambronne-lès-Ribécourt and Montmacq

Posted on 20 November 2024

TWO COMMUNES IN THE FRONT ROW

Genevieve Drela and Rémy Cuelle
Your two municipalities are the first to be affected by the Canal works since autumn 2022. What conclusions can you draw at this stage?

Geneviève Drela: It was a first, and it's surprising to see bridges emerging like this! People come to Cambronne to see it, and the residents are showing interest, even though the deforestation initially caused some concern. Today, we see the structures nearing completion, which signals the upcoming reopening of the road, and we can't wait!

Remy Cuelle: Yes, the reopening of the RD66 is highly anticipated because its closure requires
restrictive route changes for over a year. 

What does it require of elected officials and services to be at the forefront of the construction of such a project?

RC: This necessarily represents a workload for us. A quarter of my office is dedicated to the Canal plans! Before the work, with my assistants, we worked to make people understand what was going to be done and today we are continuing the work by talking with the SCSNE and the companies.
GD: It's work, meetings... but it's still a great achievement and the work is also experienced as something new.
RC: Yes, the Canal is a curiosity for the people of Montmac too!

"

“We are managing this work in consultation with the Seine-Nord Europe Canal Company and the companies.”

How are you informed about the progress of the work? And how are residents notified of disruptions?

RC: We are first informed of the upcoming steps by our contacts at the Canal Company. Then, the operations are specified as they progress, so we always know what to expect and what to indicate.

GD: The information meetings at the base camp allow us to visit the construction sites, to be in contact with the companies and to see the progress of the work for ourselves.

RC: Yes, we are also in regular direct contact with the construction companies. We share the information materials we receive from the Canal Company. Construction updates are sent by email and made available at the town hall. And the SCSNE also organizes distributions in the mailboxes of the municipalities.

GD: Yes, it's true that there is very good follow-up in terms of communication with the SCSNE.

RC: It's going well. The disruptions are real, but we're informed and people aren't surprised. For example, in the summer of 2023, we had a lot of truck traffic, but that had been clearly announced. Now, sheet piling is being driven for the construction of the spillway; the residents are well aware, even if they're not thrilled, because it's noisy…

GD: Right now, we're all just eager to get across these three beautiful bridges!

And in the future, what do you expect from the Canal in your communities?

RC: I'm waiting to see if the spillway under construction will be able to contain the floods. There are always uncertainties that remain.

GD: I hope that all the landscaping planned around the new Canal will be well carried out and I will be very attentive to the
becoming of the lateral canal to the Oise.