WORKS INFO on the territory

MONTMACQ: TRUCK TRAFFIC FROM MID-MAY 2024

What is it about ?

The excavated material from the digging of the new bed of the Oise south of Montmacq will be transported by trucks to the construction sites of the RD 66 bridges and the RD 40 bis bridge where they are used to create the ramps. Trucks leaving from the digging area located south of Montmacq will take rue du Maréchal Joffre (RD 66) to reach the construction sites of the four bridges.

When are the trucks going? 

Truck traffic in Montmacq will take place from mid-May 2024*. The traffic density will depend on the organizational conditions of the site, in particular depending on weather hazards.

 

Document

Added on May 3, 2024 - Updated on May 3, 2024

Works info: truck traffic from mid-May - Montmacq

MONTMACQ: SHEET PILE PILE PILE TESTS FROM MARCH 18, 2024​

What is it about ?

These new tests, complementary to those carried out in December 2023, aim to test the conditions for sheet pile driving, with a view to the construction of the Oise weir towards the Seine-Nord Europe Canal in Montmacq. The conclusions of these tests will make it possible to decide on the most suitable machines (hydraulic hammer or vibratory hammer) and sheet piles to use during the work phase.

When and where does this work take place?

Driving tests will be carried out from March 18, 2024 and will last a week*. They will be carried out during the day, from 8 a.m. to 18 p.m. and can generate noise and vibrations.

* Subject to weather conditions and site hazards.

Document

Added March 13, 2024 - Updated March 13, 2024

Works info 13/03/24: sheet pile driving tests - Montmacq

COMPLETION OF THE PILES OF THE BRIDGE ON THE OISE SIDE CANAL – FROM MARCH 11, 2024

What is it about ?

After the removal of the bridge over the Oise side canal and the demolition of its supports, the construction of the new bridge begins with the installation of the piles. These are reinforced concrete columns, made inside metal tubes buried in the ground which serve as a foundation for the bridge abutments.

How is the work going?

The metal steel tubes are driven into the ground by vibratory driving, then the spoil contained in the tubes is excavated by drilling to pour concrete. These operations, necessary to enable the construction of the bridge, generate vibrations and noise.

How long will the work take?

The work will be carried out alternately on the left bank then on the right bank of the Oise lateral canal from March 11, 2024 and will take place over a period of 2 to 3 weeks. *

* Subject to weather conditions and site hazards.

Document

Added March 6, 2024 - Updated March 6, 2024

Works info 06/03/24 - Construction of the piles for the bridge over the Oise lateral canal

CAMBRONNE-LÈS-RIBÉCOURT: DEMOLITION OF THE BRIDGE SUPPORTS ON THE OISE SIDE CANAL

What is it about ?
As part of the construction of the 3 bridges on the RD 66 between Montmacq and Cambronne-lès-Ribécourt, the bridge over the Oise Lateral Canal (CLO) is removed by a crane and its supports must be demolished. The space thus freed will allow the construction of the new bridge, in continuity with the two other works on the future Seine-Nord Europe Canal and on the Oise.

When does this work take place?
The demolition of the bridge supports will take place from Monday February 26 for a duration of 2 to 3 weeks*. This work, likely to generate noise or vibrations, will be carried out between 8 a.m. and 18 p.m., within the framework of the schedules provided for by the prefectural environmental authorization order.

How are they made?
A protection device is installed to prevent rubble from falling into the Oise side canal. The bridge supports are then demolished using a mechanical excavator equipped with a kind of jackhammer, called a hydraulic rock breaker (BRH).

* Subject to weather conditions and site hazards.

Document

Added February 16, 2024 - Updated February 16, 2024

Works info 16/02/24 - Cambronne-lès-Ribécourt: demolition of the bridge supports on the CLO

OISE SIDE CANAL: NAVIGATION ADJUSTMENT AND TEMPORARY CUTOFF ON FEBRUARY 21, 2024

What is it about ?
As part of the Seine-Nord Europe Canal (CSNE) works, the bridge over the Oise lateral canal, located upstream of the Bellerive lock in Cambronne-lès-Ribécourt, must be removed to allow the construction of a new bridge. This operation is scheduled for February 21, 2024 and is the subject of a notice to the inland navigation service.

How does the operation take place?
The company in charge of the work will install a crane and cradles (metal structures to stabilize the bridge during its lifting) on ​​the left bank of the Oise lateral canal. Once these elements are installed, it will lift the structure then place it on an adjacent platform in order to dismantle it.

What is the impact on navigation?
For safety reasons, during the lifting phase of the structure, navigation will be completely interrupted for a period of 2 hours*. In addition, to allow preparation for the operation, including the installation of cradles by crane, the width of the navigation channel could be reduced and specific signage put in place.

*Depending on weather conditions and site hazards.

Document

Added February 16, 2024 - Updated February 16, 2024

Work info 16/02/24 - CLO: navigation adjustment and temporary shutdown

JANUARY 2024 - PREPARATORY WORK IN CATIGNY, CAMPAGNE AND FRÉTOY-LE-CHÂTEAU

What is it about ?

Before the start of work on the Seine-Nord Europe Canal (CSNE), preventive archeology operations are carried out in Catigny, Campagne and Frétoy-le-Château in order to ensure knowledge and even the preservation of remains potentially present in the ground. .

What does this work involve?

In order to allow archaeologists to carry out their diagnosis, partial deforestation is necessary on the sites located on the rights-of-way of the future Canal. Deforestation lines will be created with widths of approximately 10 meters. These operations are carried out at a favorable time for wildlife and are supervised by an ecologist.

When and where will these interventions take place?

Preparatory work will begin from the 08 January 2024* at Bois du Quesnoy in Campagne then, in the coming weeks, around the Canal du Nord in Catigny and Bois des Queuettes in Frétoy-le-Château (see map opposite). They will take place during working hours of the week, without impacting traffic.

*Subject to weather conditions and site hazards.

Document

Added on January 5, 2024 - Updated January 5, 2024

Works info 05/01/24 - Preparatory works in Catigny, Campagne and Frétoy-le-Château

MONTMACQ: SHEET PILE PILE PILE TESTS FROM DECEMBER 18

What is it about ?

The supports of certain structures, including the Oise weir, are made up of large steel profiles, called sheet piles, interlocked edge to edge. Driving refers to the step which consists of driving the sheet piles into the ground.

What is the purpose of these tests?

They aim to test the conditions for sheet pile driving, with a view to the construction of the Oise weir towards the Seine-Nord Europe Canal in Montmacq. The conclusions of these tests will make it possible to decide on the most suitable machines (hydraulic hammer or vibratory hammer) and sheet piles to use during the work phase.

When and where does this work take place?

Driving tests will be carried out from December 18, 2023 and will last a week*. They will be carried out during the day, from 8 a.m. to 18 p.m. and can generate noise and vibrations.

Subject to weather conditions and site hazards.

Document

Added December 8, 2023 - Updated December 8, 2023

Work info 18/12/23 sheet pile driving tests - Montmacq

WORK EXEMPTION ON 01/11/23 - EARTHWORKS

What is it about ?

In order to allow staff not residing near the construction sites not to travel for a week including a non-working day, the company requested an exemption to allow its teams to work on construction sites from Monday October 30 to Thursday November 2, therefore including the 1er November.

If this exemption is granted, some truck or tractor traffic may take place but the main operations will take place within the site rights-of-way and will consist of erecting the bridge embankments. This work will take place at usual times, in accordance with the Prefectural authorization, i.e. from 8 a.m. to 18 p.m.*.

Subject to weather conditions and site hazards.

Document

Added October 25, 2023 - Updated October 25, 2023

Work info 01/11/23 - work exemption for earthworks

CONSTRUCTION OF THE RD 40 BIS: DRIVING OF METAL TUBES - PIMPREZ

What is it about ?

Construction of the RD 40 bis bridge continues with the installation of piles. Made up of metal tubes, buried in the ground then filled with concrete, they serve as the foundation for the bridge abutments.

How is the work going?

Here, the metal steel tubes are buried in the ground by driving because the nature of the terrain does not allow the use of the vibratory driving method to anchor them.

These operations generate noise and vibrations but are necessary to allow the construction of the bridge to continue.

Indeed, once the tubes are buried, they are filled with concrete, which then allows the bridge abutments to be mounted on a stabilized base.  

How long will the work take?

The driving of the metal tubes will take place, alternately on each side of the bank, from the October 9, 2023 and will last 4 to 5 weeks*. This work is carried out from Monday to Friday from 8 a.m. to 18 p.m.

Subject to weather conditions and site hazards.

Document

Added October 4, 2023 - Updated October 4, 2023

Work info 04/10/23 - driving metal tubes - Pimprez

CLOSURE OF THE RD 66 BETWEEN MONTMACQ AND CAMBRONNE FROM MONDAY SEPTEMBER 18

What is it about ?
The construction of three new bridges that will allow the RD 66 to successively span the Oise River, the future Seine-Nord Europe Canal and then the Oise side canal, is continuing in the municipalities of Montmacq and Cambronne-lès-Ribécourt – see map.
The demolition of the two existing bridges and the construction of the new route of the RD 66
are being prepared now and will be followed by the assembly of the new structures.
This sequence of works requires the complete closure of the road between Montmacq and Cambronne-lès-Ribécourt.

When and where will the departmental be cut off?
The RD 66 will be closed to all traffic from the Montmacq exit to the crossing with rue du Bac in Cambronne-lès-Ribécourt, from Monday, September 18, 2023 until autumn 2024*.

* Subject to weather conditions and site hazards.

Document

Added September 4, 2023 - Updated September 4, 2023

Info works 04/09/23 - Closure of the RD 66 between Montmacq and Cambronne from 18/09/23

SEPTEMBER 2023 - MARCH 2024 - CONTINUED DEFORESTATION FOR SECTOR 1

What is it about ?

Along the route of the Seine-Nord Europe Canal, the release of rights-of-way continues in view of the next construction sites in sector 1. The work consists, depending on the location, of rerouting networks (electricity, gas, fiber, etc.). ), demolitions of buildings or clearing of bushes and deforestation. Thus, in several municipalities in Compiégnois, a new deforestation campaign will take place this fall.

When and where does the work take place?

The main operations will take place this year in Longueil-Annel, Le Plessis-Brion, Chiry-Ourscamp and Passel – see map on the back. Work can take place Monday to Friday from 8 a.m. to 18 p.m., unless otherwise duly authorized.

Document

Added September 15, 2023

Work info September 2023 - March 2024 - continued deforestation for sector 1

TRUCK TRAFFIC THIS SUMMER - MONTMACQ / RIBÉCOURT-DRESLINCOURT

What is it about ?
As part of the work on the Seine-Nord Europe Canal (CSNE), four structures are under construction: the three RD 66 bridges between Montmacq and Cambronne-lès-Ribécourt and the "RD 40 bis" bridge between Ribécourt-Dreslincourt and Pimprez.
In order to continue the operations on these works, materials are necessary, in particular for the construction of the ramps of the bridges and must be transported from the construction site of the digging of the new bed of the Oise. Truck rotations (road tractors with semi-trailers) transporting an average of 20 tonnes of materials will therefore be carried out between Montmacq and Ribécourt-Dreslincourt.

When are the trucks going?
The movement of trucks between the CSNE worksites will begin this summer and will continue
until the end of the year*.

*Subject to weather conditions and site hazards.

Document

Added July 10, 2023 - Updated July 10, 2023

Truck traffic work info this summer - Montmacq / Ribécourt-Dreslincourt

Document

Added August 16, 2023 - Updated August 16, 2023

Info work 16/08/23 - Increased truck traffic / Montmacq

JUNE 26 – 30, 2023: DRILLING OF METALLIC TUBES - MONTMACQ

What is it about ?

As part of the work to rescinde the Oise, a temporary bridge has been put in place over the Matz to allow construction machinery to cross this watercourse, flowing from the Oise river. To make the foundations and supports for this bridge, metal tubes of about 15 meters must be driven into the ground. 

How long does this work take?

The beating of the metal tubes will be carried out discontinuously over a period of 2 to 3 days between June 26 and 30, 2023*, during the usual hours of the site, from Monday to Friday between 8 a.m. and 18 p.m.

How are metal tubes installed?

As with sheet pile driving, the tubes will be driven into the ground using a pneumatic hammer or vibratory hammer type machine.

 

* Subject to weather conditions and site hazards.

Document

Added June 19, 2023

Info Works 19/06/23 driving metal tubes - Montmacq

ACTIVITY ON THE SITE OUTSIDE WEEKDAYS - MONTMACQ / CAMBRONNE-LÈS-RIBÉCOURT

Why does work take place outside working days?

As part of the work to rescinde the Oise and the construction of the Siphon du Moulinet, certain operations require the maintenance of activity on the site over extended periods or are dependent on weather conditions. For these reasons, the company in charge of the works sometimes needs to intervene on Saturdays or public holidays.

What days and work are involved?

Thursday, May 18, 2023*: earthworks for the rescindement of the Oise and digging of the Siphon du Moulinet.

The Saturdays June 3 and 17, 2023*: digging works for the Siphon du Moulinet.

In the coming months, other operations will take place on the site, between Montmacq and Cambronne-lès-Ribécourt, on Saturdays or on public holidays. We will inform you when these works will have an impact on traffic or the generation of noise.

* Subject to weather conditions and site hazards.

Document

Added on May 15, 2023 - Updated on May 15, 2023

Info Works 15/05/23 - Activity on the site outside working days

APRIL 26 - MAY 3: PILE DRIVING - MONTMACQ

What is it about ? 

As part of the construction of a temporary bridge over the Oise, allowing the companies in charge of the work to access certain areas of the site, piles will be driven from time to time in order to build the foundations and supports of the bridge.

What is the duration of these works*?

Pile driving will take place punctually from April 26 to May 03, 2023 from Monday to Saturday between 8 a.m. and 18 p.m.

* Subject to weather conditions and site hazards.

Document

Added April 26, 2023

Info Works 26/04/23 pile driving - Montmacq

MARCH 31 - MAY 26: EXTENDED REEL SIPHON WORK HOURS EXPANDED

What changes and for how long?

The hours of the construction site must finally remain extended from 6AM to 22PM over the periods of March 31 to May 26, 2023* (Saturday included but not Sunday).

*Subject to weather conditions and site hazards.

Document

Added March 29, 2023 - Updated March 29, 2023

Info Works 31/03/23 Siphon du Moulinet - extension of the extended working hours

MARCH 22: BEGINNING OF WORK ON THE "RD 40 BIS" BRIDGE - PIMPREZ

What works have been carried out?

Construction work on the "RD 40 bis" bridge began with the installation of sheet piles to support and reinforce the ground of the service road which will be created after the construction of the bridge abutments.

How are they going?

This stage consists of driving large steel sections into the ground by vibro-driving and then, in a second step, carrying out the piling to finalize their anchoring in their ground. If the vibratory driving is hardly perceptible, the driving of the sheet piles generates noise during its realization. It is however necessary to finalize the sinking of the sheet piles.

What is the duration* of the work?

The first sheet pile driving tests took place from March 22 and operations will continue until the end of March.

The work will take place from Monday to Friday from 8 a.m. to 18 p.m.

* Under adverse weather conditions and site hazards

Document

Added March 24, 2023 - Updated March 24, 2023

Info Works 24/03/23 "RD 40 bis" bridge - Pimprez

MARCH 13 - APRIL 22: MODIFICATION OF THE HOURLY AMPLITUDE OF THE REEL SIPHON WORKS

What changes and for how long?

Construction hours will be extended from 6AM to 22PM over the following periods*:

  • Du March 13 to March 31, 2023 (Saturday included but not Sunday),
  • Du April 17 to April 28, 2023 (Saturday included but not Sunday).

Why are the hours extended?

The creation of this work consists in digging a micro tunnel (with a diameter of approximately 1m), passing under the future Canal Seine-Nord Europe to allow the watercourse of the Moulinet to join the new bed of the Oise. The micro-tunnelling machine – the machine used to build the tunnel – needs to operate over extended hours to progress because, in addition to digging the ground, it also lays the walls of the tunnel, thus making it possible to stabilize it. These operations must be carried out over long amplitudes.

*Subject to weather conditions and site hazards.

Document

Added March 10, 2023 - Updated March 10, 2023

Info Works 13/03/23 Siphon du Moulinet

NOVEMBER 28 - DECEMBER 2, 2022: CUTTING THE RD 66 BETWEEN MONTMACQ AND CAMBRONNE​

What is it about ?

Work to rescinde the Oise along the RD66 began this summer and is entering a phase which requires the temporary interruption of all traffic between Montmacq and Cambronne-lès-Ribécourt to guarantee the safety of users and personnel working on the building site.

When will the county be cut off?

The RD 66 will be closed days and nights, from Monday November 28 to Friday December 2, 2022 included*. The companies managed to limit the road closure to just 1 week instead of the 4 announced. The bridges crossing the Oise and the side canal to the Oise will be inaccessible over the period.

* Subject to weather conditions and site hazards.

Document

Added on November 17, 2022 - Updated on November 23, 2022

Info Works 21/11/22 Montmacq / Cambronne

BEAURAINS-LÈS-NOYON: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

The work essentially consists of exploiting the poplar plantation and replanting alluvial afforestation. Ponds will also be created.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Trucks to evacuate excavated soil and cut wood will circulate over the period. Alternating traffic will be put in place from time to time. The other interventions (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated November 23, 2022

Info works 22/08/22 Beaurains-lès-Noyon

PIMPREZ – CHIRY-OURSCAMP: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

Shallow planting and earthworks are carried out, in particular to create ponds and restore backwaters favorable to biodiversity.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Excavated earth evacuation trucks will circulate over the period. The other operations (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated November 23, 2022

Works info 22/08/22 Pimprez / Chiry-Ourscamp

MORLINCOURT: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

Environmental planting and shallow earthworks are being carried out to the east of the village, along the Oise side canal, in particular to restore wetlands and create ponds favorable to biodiversity.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Excavated earth evacuation trucks will circulate over the period. Alternating traffic will be put in place from time to time. The other interventions (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated November 23, 2022

Info works 22/08/22 Morlincourt

CAMBRONNE-LÈS-RIBÉCOURT: DEMOLITION OF BUILDINGS IN MAY 2022

What works are carried out?

Four houses in Cambronne-lès-Ribécourt must be destroyed to allow the construction of a new bridge over the side canal to the Oise. At the same time, network rerouting operations (water, electricity, telephone, etc.) are carried out by concessionaires.

When and how does this work take place?

Work will begin between May 2 and May 6 and will last approximately 5 weeks*. They will take place from Monday to Friday, between 8 a.m. and 18 p.m. They will generate noise and unusual machinery traffic. For everyone's safety, the bottom of rue du Bac may occasionally be closed to road traffic during these 5 weeks.

*subject to weather conditions and site hazards.

Edit 19/05: the demolition work will start from June 1, 2022. Indeed, the visit of the ecologist highlighted the presence of birds whose breeding period requires delaying the work.

Document

Added on April 4, 2022 - Updated on November 23, 2022

WORKS INFO 04/04/22 CAMBRONNE

Demolition of buildings

RIBÉCOURT / PIMPREZ: SHEET PILE INSTALLATION WORK BETWEEN FEBRUARY AND APRIL 2022

What works are carried out?

Construction of the Canal quays at Ribécourt-Dreslincourt and Pimprez is continuing and sheet pile driving will take place on both sites. This stage consists of driving large steel sections into the ground intended to retain the earth and serve as a support for the quay. The sheet pile wall also contributes to sealing the walls of the Canal.

What is the duration* of the work?

The driving of sheet piles on the 200 meters of linear quay at Pimprez and the 150 meters of quay at Ribécourt-Dreslincourt is planned between mid-February and mid-April 2022. Work will take place on weekdays and during the day only, Monday to Friday, between 8 a.m. and 18 p.m.

*subject to weather conditions and site hazards.

Edit 25/02: the sheet piles are being delivered, and driving will start on March 8.

Edit 12/04: after the first successful vibrosinking operations, the rest of the work requires the initially announced sheet pile driving, which will continue until the end of April.

 

Document

Added February 6, 2022 - Updated November 23, 2022

WORKS INFO 06/02/22 RIBÉCOURT / PIMPREZ

Installation of sheet piles

MONTMACQ: SHEET PILE DRIVING TESTS IN JULY 2021

What is it about ?

The watertight walls of water retaining structures are made up of large steel sections, called sheet piling, interlocked edge to edge. Driving refers to the step that consists of driving the sheet piles into the ground.

When and where does this work take place?

The work will take place in Montmacq during the day, Monday to Friday, over 2 to 4 weeks during July 2021* (behind the ADP ponds).

*subject to weather conditions and site hazards.

Document

Added June 28, 2021 - Updated November 23, 2022

WORK INFO 28/06/21 MONTMACQ

Sheet pile driving tests

RIBÉCOURT / CAMBRONNE: SHEET PILE DRIVING TESTS IN JULY 2021

What is it about ?

The watertight walls of water retaining structures are made up of large steel sections, called sheet piling, interlocked edge to edge. Driving refers to the step that consists of driving the sheet piles into the ground.

When and where does this work take place?

The work will take place during the day, Monday to Friday, over 2 to 4 weeks during July 2021* (at the “Quai SECO”, along the towpath).

*subject to weather conditions and site hazards

Document

Added June 28, 2021 - Updated November 23, 2022

WORKS INFO 28/06/21 RIBÉCOURT / CAMBRONNE

Sheet pile driving tests