Compiégnois-Noyonnais territory

WORKS INFO on the territory

MONTMACQ BRIDGE - RUE DU GÉNÉRAL MANGIN: ROAD CLOSURE FROM APRIL 28, 2025 - ERRATUM

What is it about ? 

As part of the work on the Montmacq – Cambronne-lès-Ribécourt lock, spoil has been brought into the construction site area from the other side of the Thourotte Montmacq municipal road for several weeks. The number of dump trucks carrying this spoil is expected to increase significantly and requires the closure of rue Roger Martin (Montmacq bridge) and rue du Général Mangin (Thourotte side) from Monday, April 28, 2025.

ERRATUM: the closure of rue Roger Martin and rue du Général Mangin will ultimately not be effective no earlier than May 5 and no later than May 7, 2025*. 

How long will the road be closed?

Between Thourotte and Montmacq, the Seine-Nord Europe Canal (CSNE) will be inserted between the Oise Lateral Canal and the Oise River. The two existing bridges will also be demolished and replaced by two new bridges, and a new bridge will be built to cross the CSNE. The bridge over the Oise will be the first to be demolished in 2026 while bridge over the Oise lateral canal will be demolished in 2027*.
For safety reasons, given the state of the current structures, the Thourotte-Montmacq municipal road will remain closed to vehicle traffic until the completion of the three new structures, i.e. by 2028*.

If safety conditions are met, cycle and pedestrian paths may be temporarily reauthorised before the demolition of the structures.

*Depending on construction site conditions.

Document

Added April 28, 2025 - Updated April 28, 2025

Work information: ERRATUM Montmacq bridge – Rue du Général Mangin: road closure from week 19

Document

Added April 16, 2025 - Updated April 16, 2025

Roadworks information: Montmacq Bridge - Rue du Général Mangin: road closure from 28/04/25

INFO ON BOATING: EXTENSION OF NAVIGATION RESTRICTIONS FROM APRIL TO JUNE 2025 – WORK ON THE NOYON QUAY ON THE CANAL DU NORD

What is it about ? 

The construction of a quay works on the Canal du Nord is underway in Noyon. It will mainly be used for the supply of materials for the Noyon lock worksThe Seine-Nord Europe Canal Company has indeed undertaken to create favorable conditions for the massification of waterway transport during the construction. This involves in particular: the introduction of a modal shift clause in works contracts, thus ensuring a reduction in CO emissions2 of the site.

What work has an impact on navigation?

Various operations for the connection of the new quay with the banks of the Canal du Nord (sawing and demolition of the banks then waterproofing) and the installation of the equipment will be carried out between April and June 2025* and will result in navigation restrictions. 

* Depending on weather conditions and construction site hazards.

Document

Added April 10, 2025 - Updated April 10, 2025

Shipping information: extension of navigation restrictions on the CDN at Noyon from April to June

RESUMPTION OF SHEET PILE DRIVING FROM APRIL 1, 2025 - MONTMACQ

What is it about ?

The works of the construction of the spillway from Montmacq will resume 1er April 2025Indeed, the deadlines initially communicated in the work flash of September 9, 2024 had to be adjusted due to the bad weather this winter which postponed certain operations. Sheet piles, allowing the support of the structure to be carried out, will be driven down to depths of 15 meters into the ground using a vibratory hammer (in the upper part of the ground) then a hydraulic hammer (in the lower part, for very hard ground).

When does the work take place?

The Sheet pile installation work will resume on the 1ster April 2025 et
will last until end of June 2025*. These operations will be carried out from Monday to Friday, excluding public holidays, during the day, from 8 a.m. to 18 p.m. and may generate noise and vibrations.

*Subject to weather conditions and construction site hazards. 

Document

Added March 27, 2025

Work information: sheet pile driving to resume from April 1st - Montmacq

MONTMACQ BRIDGE – RUE DU GÉNÉRAL MANGIN: ALTERNATING TRAFFIC FROM MARCH 12, 2025

What is it about ?
The construction of the Montmacq – Cambronne-lès-Ribécourt lock begins with the installation of tracks and construction site facilities in preparation for secure the perimeter of operations and to maintain the work areas above water upstream of the civil engineering phasesIn this context, debris located on the other side of the Thourotte – Montmacq municipal road (rue du général Mangin) must be transported by dumper to the work zone. These movements involve crossing the road at a rate of several rotations per hour., traffic is arranged to guarantee everyone's safety and an alternation is put in place.

How will traffic be organized?
To avoid traffic jams on the structures and to adjust the alternation of traffic as best as possible, signallers will be positioned upstream of the Thourotte bridges (rue du Général Mangin) and Montmacq (rue Roger Martin) to ensure the passage of vehicles in one direction then the other. In addition, another person will be positioned at the level of the crossing of the machines in the middle of the municipal road – see plan opposite. This alternation will be indicated on each side of the road by signs and the road will be cleaned as needed.
For everyone's safety, we thank you for ensuring that you respect the signs and to the safety of the signallers working on this operation.

When are these developments planned?
Traffic will alternate from of March 12 2025 for a few weeks,
du Monday to Friday, 8 a.m. to 12 p.m. and 13 p.m. to 18 p.m., upstream of the road closure.

Document

Added March 11, 2025 - Updated March 19, 2025

Work information: Montmacq bridge - Rue du Général Mangin: alternating traffic from March 12, 2025

RELEASE OF RIGHT-OF-WAY: CREATION OF ACCESS FOR THE BURIED THOUTOTTE NETWORK – FROM MARCH 13, 2025

What is it about ?

To enable the creation of the Seine-Nord Europe Canal, a network diversion is necessary between Ressons-sur-Matz and Thourotte near the football ground and from mid-March 2025.

What operations are carried out?

The Seine-Nord Europe Canal Company will create an additional access portal along the railway line to allow the passage of machinery needed to carry out surveys for the works (see plan opposite).

The construction of this new access will begin on Thursday March 13, 2025Once in place, it will allow companies to access the construction site area which will be marked out to ensure everyone's safety.

Document

Added March 11, 2025 - Updated March 19, 2025

Work information: release of rights-of-way - creation of access for burying the network - Thourotte from March 13, 2025

REOPEN OF THE RD66 BETWEEN MONTMACQ AND CAMBRONNE-LÈS-RIBÉCOURT

A first restoration put into service 

The new departmental road 66, between Montmacq and Cambronne-lès-Ribécourt, has just been reopened to traffic this Tuesday March 4, 2025. Vehicles can use it but some operations are still necessary for its completion, in particular to allow pedestrians and cyclists to use the greenway. This should be open. May 2025.

What work has been done? 

This first road restoration carried out as part of the work of the CSNE is composed of 3 books which cross three waterways; the Oise, the future Seine-Nord Europe Canal (CSNE) and the Oise lateral canal (CLO). 

Discover the steps of production of these works in video.

SHEET PILES INSTALLATION WORK FROM MARCH 3, 2025 - NOYON

What work has been carried out?

The construction of the Noyon quay continues and sheet pile driving will take place
place on the construction site. This step consists of drive large steel profiles into the ground, intended to retain the earth and serve as support for the quay. The sheet pile wall also helps to ensure the watertightness of the Canal walls.

How do they take place?
The technique involves tapping the sheet piles into the ground until they become anchored in the chalk. Sheet piles, measuring 10 to 12 meters long, are driven into the ground by vibration (vibrodriving) and sometimes, depending on the nature of the ground, using a pneumatic hammer. This step generates noise and vibrations in the immediate vicinity of the work.

What is the duration of the work?
The driving of sheet piles, on the 100 linear meters of the Noyon quay, is planned between 3 and 21 March 2025*. The work will take place during the week and during the day only, from 8 a.m. to 17 p.m.*.

* Subject to weather conditions and site hazards.

Document

Added February 20, 2025 - Updated March 19, 2025

Work info: installation of sheet piles from 03/03/25 - Noyon

DEFORESTATION IN VAUCHELLES AND PORQUÉRICOURT FROM THE END OF FEBRUARY

What is it about ?
Along the route of the Seine-Nord Europe Canal, the release of rights-of-way continues in
view of the upcoming construction sites in sector 2. The works consist, depending on the location, of
network diversions (electricity, gas, fiber, etc.), demolitions of buildings or
clearing and deforestation. Thus, deforestation will be carried out in Vauchelles and Porquéricourt.

Where and when is the work taking place?
Deforestation will take place in the area that will be subject to redevelopment work
traffic between the RD 932 and RD 934 – see map opposite. This work will take place between February 24 and March 15, 2025*. They will be carried out during the day, from Monday to Friday. Other areas, located in the Seine-Nord Europe Canal in Noyonnais, will also be subject to deforestation campaigns, starting in winter 2025.

*Subject to weather conditions and construction site hazards.

Document

Added February 20, 2025 - Updated March 24, 2025

Work information: deforestation from the end of February 2025 - Vauchelles and Porquéricourt

DEFORESTATION IN NOYON FROM THE END OF FEBRUARY

What is it about ?
Along the route of the Seine-Nord Europe Canal, the release of rights-of-way continues in
view of the upcoming construction sites in sector 2. The works consist, depending on the location, of
network diversions (electricity, gas, fiber, etc.), demolitions of buildings or
clearing and deforestation. Thus, deforestation will be carried out in Noyon in the lock area.

Where and when is the work taking place?
Deforestation will take place on both sides of the RD 938 in the area that will host
the Noyon lock – see plan on the back. This work will take place between February 24 and the
March 15, 2025*They will be carried out during the day, from Monday to Friday.
Other areas, located within the Seine-Nord Europe Canal in Noyon, will be
also the subject of deforestation campaigns, starting in winter 2025.

*Subject to weather conditions and construction site hazards.

Document

Added February 20, 2025 - Updated March 24, 2025

Work info: deforestation from the end of February 2025 - Noyon

CONDUCTION OF GEOTECHNICAL SURVEYS FROM 18/02/25 - LE PLESSIS-BRION

What is it about ?

As part of the construction of the Seine-Nord Europe Canal, a junction between the Oise and the future Canal will be built at the level of the commune of Plessis-Brion.

Prior to the work, geotechnical surveys are necessary on the banks of the Oise in order to assess the quality of the soil on the banks. These surveys were planned for October 2024 but could not be carried out due to the presence of concrete blocks on the banks. The company had to adapt its equipment and intervention methodology and will carry out the surveys in February.

When are the surveys carried out? 

The interventions will take place between February 18 and 20, 2025*. They will be carried out during the day and may generate noise.

* Subject to weather conditions and site hazards.

Document

Added February 14, 2025 - Updated March 24, 2025

Work info: geotechnical surveys to be carried out from 18/02/25 - Le Plessis-Brion

PLANTATIONS ON THE BANKS OF THE OISE FROM 17/02/25 - MONTMACQ

What is it about ?

The rescission of Oise having been finalized, The first phase of development of the river banks can begin. Companions will therefore be required to intervene in the immediate vicinity of the gardens of the residents of rue Joffre in Montmacq in the coming weeks to plant shrubs.

What species are planted?

The plantations will mix nearly 14 young shoots of shrubs of local species which will recreate, once adult, a natural riparian forest, in accordance with the principles adopted in consultation. Among these species are three-stamen willows, basket willows, hawthorn, dogwoods and even buckthorn.

In order to recreate a dense and varied environment in a few years, young plants of field maple, alder, black poplar, white willow or even smooth and field elm will also be planted on the banks of the Oise.

When will the plantings take place?

Plantings are carried out in winter when the soil is waterlogged in order to encourage the plants to take root. They will begin February 17, 2025*, and will be carried out over a period of approximately 3 weeks*.

*Depending on weather conditions and construction site hazards. 

Document

Added February 7, 2025 - Updated March 24, 2025

Work info: plantations on the banks of the Oise from 17/02/25 - Montmacq

EXTENSION OF THE CLOSURE OF THE RD66 BETWEEN MONTMACQ AND CAMBRONNE-LÈS-RIBÉCOURT

Where are we ? 

The construction of the bridges on the RD 66 between Montmacq and Cambronne-lès-Ribécourt is being finalized. Work is currently focusing on the completion of the reroad clothes, security equipment and road markings as well as the construction of sanitation basins. 

The Weather conditions in winter 2023-2024 and early autumn have put the phasing of construction sites to the test and impose an additional delay to complete these operations in order to make the new road safe for traffic before it is put back into service.
Aware of the inconvenience caused, the Group in charge of operations and the Seine-Nord Europe Canal Company join together to thank you for your patience.

How long will the road remain closed?

The teams are doing everything possible to enable the road to be put back into service in
link with the services of the Oise Department from the start of the year. The goal is a
reopening on February 13, 2025*
, depending on weather conditions and construction site hazards. 

* ERRATUM: lThe weather conditions of recent weeks (heavy rainfall and flooding) have had an impact on the expected deadlines. The target for reopening is early March 2025.

Document

Added November 12, 2024 - Updated March 24, 2025

Works information: extension of the closure of the RD66 between Montmacq and Cambronne-lès-Ribécourt

CONDUCTION OF GEOTECHNICAL SURVEYS FROM OCTOBER 28, 2024 – LE PLESSIS-BRION

What is it about ?

As part of the construction of the Seine-Nord Europe Canal, a junction between the Oise and the future Canal will be built at the level of the commune of Plessis-Brion.

Prior to the work, geotechnical surveys are necessary on the banks of the Oise in order to assess the quality of the soil on the banks.

Core drilling will be carried out to extract soil samples to visualize the different layers of materials and analyze their composition.

When are the surveys carried out?

The interventions will begin on 28 October 2024 and will extend over the whole week*. They will be carried out during the day and may generate noise.

Document

Added October 28, 2024 - Updated March 24, 2025

Work info: geotechnical surveys from October 28, 2024 - Le Plessis-Brion

PREPARATORY WORK: DEFORESTATION FROM THE END OF SEPTEMBER IN NOYON

What is it about ?

THEenvironmental authorization, issued by State services on August 9, 2024, allows work to begin on sectors 2 to 4 of the Seine-Nord Europe Canal route. Among the first operations, work to free up rights-of-way (network diversions, demolitions, deforestation) will take place in the area, including initial deforestation in Noyon.

Where and when is the work taking place?

The deforestation will take place near the current lock on the Canal du Nord, on the bank
west of the canal, as well as at the level of the greenway towards Larbroye upstream of the bridge – see
plan opposite.

These works will take place during the day, Monday to Friday, between the end of September and
beginning of October.


Other areas, particularly those located within the boundaries of the future lock of the Seine-Nord Europe Canal in Noyon, will also be the subject of deforestation campaigns, starting in winter 2025.

Document

Added September 23, 2024 - Updated March 24, 2025

Work info: deforestation from the end of September in Noyon

CONTINUATION OF DEFORESTATION AND CLEARING FOR SECTOR 1

What is it about ?

Along the Seine-Nord Europe Canal route, the release of rights-of-way continues in preparation for the upcoming works between Compiègne and Passel. A new deforestation and clearing campaign will take place from mid-September.

Where and when is the work taking place?
For the 2024-2025 campaign, deforestation and clearing operations
take place along the entire route in Compiègne.

Clearing mainly concerns areas that have been deforested in the years
previous ones in order to maintain the plots and their accesses before the work.

The work will take place between September 2024 and March 2025, Monday to Friday, 8 a.m. to 18 p.m.*, except for duly authorized exceptions. All interventions are shown on the plan opposite.

*Subject to weather conditions and construction site hazards. 

Document

Added September 12, 2024 - Updated March 24, 2025

Work information: continuation of deforestation and clearing for sector 1

Focus on the interventions planned in the municipalities of Longueil-Annel, Le Plessis-Brion and Thourotte. 

In Longueil-Annel, Le Plessis-Brion and Thourotte, these operations are planned at the level of Canal route as well as in the areas which will be the subject ofecological compensatory developments

The clearing planned this year concern areas that were deforested in previous years in order tomaintain the plots and their accesses before the work begins.


Furthermore, in the areas with ecological issues, barriers are put in place upstream of operations to demarcate them and thus prevent small wildlife from accessing the work areas. These barriers may sometimes cross paths and then require a course adjustment.

Document

Added September 13, 2024 - Updated March 24, 2025

Work info: continuation of deforestation and clearing - Le Plessis-Brion, Longueil-Annel, Thourotte

Focus on the planned interventions in Pimprez

In Pimprez, these operations are planned at the level of Canal route as well as in the areas which will be the subject ofecological compensatory developments

Furthermore, in areas with ecological challenges, barriers are put in place in upstream of operations to delimit them and thus prevent small fauna from accessing them areas under construction.

Document

Added September 13, 2024 - Updated March 24, 2025

Work info: continuation of deforestation and clearing - Pimprez

MONTMACQ: SHEET PILE DRIVING FROM SEPTEMBER 16, 2024

What is it about ?

After several sheet pile driving tests at the end of 2023 and in March 2024, the works
Construction work on the Oise spillway towards the Seine-Nord Europe Canal at Montmacq will begin on September 19

Les sheet piles, large steel profiles to support this 502-meter structure, will be sunk to depths of depths of 15 meters into the ground using a vibratory hammer (in the upper part of the ground) then a hydraulic hammer (in the lower part, for very hard ground).

When and where does this work take place?

The Sheet pile installation work will begin on September 19, 2024 et
will last between three and four months*. These operations will be carried out during the day, 8 a.m. to 18 p.m. and may generate noise and vibrations.
Prior to the operations, the installation of the machines will take place from September 16 and the first deliveries of sheet piles will begin on September 18.

*Subject to weather conditions and site hazards.

Document

Added September 2, 2024 - Updated March 24, 2025

Work info: sheet pile driving from 19/09 - Montmacq

CAMBRONNE-LÈS-RIBÉCOURT: CLOSURE OF RUE DU BAC - JULY 15, 2024

What is it about ?

To allow the continuation of the work on the bridge over the Oise side canal, carried out near the descent of Rue du Bac, it will be closed to traffic from July 15 until the end of December 2024*.

What are the traffic arrangements?

During the period of road closure, no vehicle will be able to drive or park on the descent of rue du Bac. Access to the latter and the towpath will be from the top of the street, at the railway level (see map opposite.

* Subject to weather conditions and site hazards.

Document

Added July 8, 2024 - Updated March 24, 2025

Work information: closure of rue du bac - Cambronne-lès-Ribécourt

MONTMACQ: EXPANSION OF WORK TIMES

What is it about ?

Work hours are extended from 7:30 a.m. to 19 p.m. until the end of summer*. All of the work is concerned: earthworks and civil engineering on the structures between Montmacq and Cambronne-lès-Ribécourt as well as in Pimprez. The extension of the opening hours allows the company to increase the daily volume of earthworks to reduce the duration of these operations.

* Subject to weather conditions and site hazards.

Document

Added June 11, 2024 - Updated March 24, 2025

Works info: extension of work schedules - Montmacq

MONTMACQ: TRUCK TRAFFIC FROM MID-MAY 2024

What is it about ?

The excavated material from the digging of the new bed of the Oise south of Montmacq will be transported by trucks to the construction sites of the RD 66 bridges and the RD 40 bis bridge where they are used to create the ramps. Trucks leaving from the digging area located south of Montmacq will take rue du Maréchal Joffre (RD 66) to reach the construction sites of the four bridges.

When are the trucks going? 

Truck traffic in Montmacq will take place from mid-May 2024*. The traffic density will depend on the organizational conditions of the site, in particular depending on weather hazards.

 

Document

Added May 3, 2024 - Updated March 24, 2025

Works info: truck traffic from mid-May - Montmacq

MONTMACQ: SHEET PILE PILE PILE TESTS FROM MARCH 18, 2024​

What is it about ?

These new tests, complementary to those carried out in December 2023, aim to test the conditions for sheet pile driving, with a view to the construction of the Oise weir towards the Seine-Nord Europe Canal in Montmacq. The conclusions of these tests will make it possible to decide on the most suitable machines (hydraulic hammer or vibratory hammer) and sheet piles to use during the work phase.

When and where does this work take place?

Driving tests will be carried out from March 18, 2024 and will last a week*. They will be carried out during the day, from 8 a.m. to 18 p.m. and can generate noise and vibrations.

* Subject to weather conditions and site hazards.

Document

Added March 13, 2024 - Updated March 24, 2025

Works info 13/03/24: sheet pile driving tests - Montmacq

COMPLETION OF THE PILES OF THE BRIDGE ON THE OISE SIDE CANAL – FROM MARCH 11, 2024

What is it about ?

After the removal of the bridge over the Oise side canal and the demolition of its supports, the construction of the new bridge begins with the installation of the piles. These are reinforced concrete columns, made inside metal tubes buried in the ground which serve as a foundation for the bridge abutments.

How is the work going?

The metal steel tubes are driven into the ground by vibratory driving, then the spoil contained in the tubes is excavated by drilling to pour concrete. These operations, necessary to enable the construction of the bridge, generate vibrations and noise.

How long will the work take?

The work will be carried out alternately on the left bank then on the right bank of the Oise lateral canal from March 11, 2024 and will take place over a period of 2 to 3 weeks. *

* Subject to weather conditions and site hazards.

Document

Added March 6, 2024 - Updated March 24, 2025

Works info 06/03/24 - Construction of the piles for the bridge over the Oise lateral canal

CAMBRONNE-LÈS-RIBÉCOURT: DEMOLITION OF THE BRIDGE SUPPORTS ON THE OISE SIDE CANAL

What is it about ?
As part of the construction of the 3 bridges on the RD 66 between Montmacq and Cambronne-lès-Ribécourt, the bridge over the Oise Lateral Canal (CLO) is removed by a crane and its supports must be demolished. The space thus freed will allow the construction of the new bridge, in continuity with the two other works on the future Seine-Nord Europe Canal and on the Oise.

When does this work take place?
The demolition of the bridge supports will take place from Monday February 26 for a duration of 2 to 3 weeks*. This work, likely to generate noise or vibrations, will be carried out between 8 a.m. and 18 p.m., within the framework of the schedules provided for by the prefectural environmental authorization order.

How are they made?
A protection device is installed to prevent rubble from falling into the Oise side canal. The bridge supports are then demolished using a mechanical excavator equipped with a kind of jackhammer, called a hydraulic rock breaker (BRH).

* Subject to weather conditions and site hazards.

Document

Added February 16, 2024 - Updated March 24, 2025

Works info 16/02/24 - Cambronne-lès-Ribécourt: demolition of the bridge supports on the CLO

OISE SIDE CANAL: NAVIGATION ADJUSTMENT AND TEMPORARY CUTOFF ON FEBRUARY 21, 2024

What is it about ?
As part of the Seine-Nord Europe Canal (CSNE) works, the bridge over the Oise lateral canal, located upstream of the Bellerive lock in Cambronne-lès-Ribécourt, must be removed to allow the construction of a new bridge. This operation is scheduled for February 21, 2024 and is the subject of a notice to the inland navigation service.

How does the operation take place?
The company in charge of the work will install a crane and cradles (metal structures to stabilize the bridge during its lifting) on ​​the left bank of the Oise lateral canal. Once these elements are installed, it will lift the structure then place it on an adjacent platform in order to dismantle it.

What is the impact on navigation?
For safety reasons, during the lifting phase of the structure, navigation will be completely interrupted for a period of 2 hours*. In addition, to allow preparation for the operation, including the installation of cradles by crane, the width of the navigation channel could be reduced and specific signage put in place.

*Depending on weather conditions and site hazards.

Document

Added February 16, 2024 - Updated March 24, 2025

Work info 16/02/24 - CLO: navigation adjustment and temporary shutdown

JANUARY 2024 - PREPARATORY WORK IN CATIGNY, CAMPAGNE AND FRÉTOY-LE-CHÂTEAU

What is it about ?

Before the start of work on the Seine-Nord Europe Canal (CSNE), preventive archeology operations are carried out in Catigny, Campagne and Frétoy-le-Château in order to ensure knowledge and even the preservation of remains potentially present in the ground. .

What does this work involve?

In order to allow archaeologists to carry out their diagnosis, partial deforestation is necessary on the sites located on the rights-of-way of the future Canal. Deforestation lines will be created with widths of approximately 10 meters. These operations are carried out at a favorable time for wildlife and are supervised by an ecologist.

When and where will these interventions take place?

Preparatory work will begin from the 08 January 2024* at Bois du Quesnoy in Campagne then, in the coming weeks, around the Canal du Nord in Catigny and Bois des Queuettes in Frétoy-le-Château (see map opposite). They will take place during working hours of the week, without impacting traffic.

*Subject to weather conditions and site hazards.

Document

Added January 5, 2024 - Updated March 24, 2025

Works info 05/01/24 - Preparatory works in Catigny, Campagne and Frétoy-le-Château

MONTMACQ: SHEET PILE PILE PILE TESTS FROM DECEMBER 18

What is it about ?

The supports of certain structures, including the Oise weir, are made up of large steel profiles, called sheet piles, interlocked edge to edge. Driving refers to the step which consists of driving the sheet piles into the ground.

What is the purpose of these tests?

They aim to test the conditions for sheet pile driving, with a view to the construction of the Oise weir towards the Seine-Nord Europe Canal in Montmacq. The conclusions of these tests will make it possible to decide on the most suitable machines (hydraulic hammer or vibratory hammer) and sheet piles to use during the work phase.

When and where does this work take place?

Driving tests will be carried out from December 18, 2023 and will last a week*. They will be carried out during the day, from 8 a.m. to 18 p.m. and can generate noise and vibrations.

Subject to weather conditions and site hazards.

Document

Added December 8, 2023 - Updated December 8, 2023

Work info 18/12/23 sheet pile driving tests - Montmacq

WORK EXEMPTION ON 01/11/23 - EARTHWORKS

What is it about ?

In order to allow staff not residing near the construction sites not to travel for a week including a non-working day, the company requested an exemption to allow its teams to work on construction sites from Monday October 30 to Thursday November 2, therefore including the 1er November.

If this exemption is granted, some truck or tractor traffic may take place but the main operations will take place within the site rights-of-way and will consist of erecting the bridge embankments. This work will take place at usual times, in accordance with the Prefectural authorization, i.e. from 8 a.m. to 18 p.m.*.

Subject to weather conditions and site hazards.

Document

Added October 25, 2023 - Updated March 24, 2025

Work info 01/11/23 - work exemption for earthworks

CONSTRUCTION OF THE RD 40 BIS: DRIVING OF METAL TUBES - PIMPREZ

What is it about ?

Construction of the RD 40 bis bridge continues with the installation of piles. Made up of metal tubes, buried in the ground then filled with concrete, they serve as the foundation for the bridge abutments.

How is the work going?

Here, the metal steel tubes are buried in the ground by driving because the nature of the terrain does not allow the use of the vibratory driving method to anchor them.

These operations generate noise and vibrations but are necessary to allow the construction of the bridge to continue.

Indeed, once the tubes are buried, they are filled with concrete, which then allows the bridge abutments to be mounted on a stabilized base.  

How long will the work take?

The driving of the metal tubes will take place, alternately on each side of the bank, from the October 9, 2023 and will last 4 to 5 weeks*. This work is carried out from Monday to Friday from 8 a.m. to 18 p.m.

Subject to weather conditions and site hazards.

Document

Added October 4, 2023 - Updated March 24, 2025

Work info 04/10/23 - driving metal tubes - Pimprez

CLOSURE OF THE RD 66 BETWEEN MONTMACQ AND CAMBRONNE FROM MONDAY SEPTEMBER 18

What is it about ?
The construction of three new bridges that will allow the RD 66 to successively span the Oise River, the future Seine-Nord Europe Canal and then the Oise side canal, is continuing in the municipalities of Montmacq and Cambronne-lès-Ribécourt – see map.
The demolition of the two existing bridges and the construction of the new route of the RD 66
are being prepared now and will be followed by the assembly of the new structures.
This sequence of works requires the complete closure of the road between Montmacq and Cambronne-lès-Ribécourt.

When and where will the departmental be cut off?
The RD 66 will be closed to all traffic from the Montmacq exit to the crossing with rue du Bac in Cambronne-lès-Ribécourt, from Monday, September 18, 2023 until autumn 2024*.

* Subject to weather conditions and site hazards.

Document

Added September 4, 2023 - Updated March 24, 2025

Info works 04/09/23 - Closure of the RD 66 between Montmacq and Cambronne from 18/09/23

SEPTEMBER 2023 - MARCH 2024 - CONTINUED DEFORESTATION FOR SECTOR 1

What is it about ?

Along the route of the Seine-Nord Europe Canal, the release of rights-of-way continues in view of the next construction sites in sector 1. The work consists, depending on the location, of rerouting networks (electricity, gas, fiber, etc.). ), demolitions of buildings or clearing of bushes and deforestation. Thus, in several municipalities in Compiégnois, a new deforestation campaign will take place this fall.

When and where does the work take place?

The main operations will take place this year in Longueil-Annel, Le Plessis-Brion, Chiry-Ourscamp and Passel – see map on the back. Work can take place Monday to Friday from 8 a.m. to 18 p.m., unless otherwise duly authorized.

Document

Added September 15, 2023 - Updated March 24, 2025

Work info September 2023 - March 2024 - continued deforestation for sector 1

TRUCK TRAFFIC THIS SUMMER - MONTMACQ / RIBÉCOURT-DRESLINCOURT

What is it about ?
As part of the work on the Seine-Nord Europe Canal (CSNE), four structures are under construction: the three RD 66 bridges between Montmacq and Cambronne-lès-Ribécourt and the "RD 40 bis" bridge between Ribécourt-Dreslincourt and Pimprez.
In order to continue the operations on these works, materials are necessary, in particular for the construction of the ramps of the bridges and must be transported from the construction site of the digging of the new bed of the Oise. Truck rotations (road tractors with semi-trailers) transporting an average of 20 tonnes of materials will therefore be carried out between Montmacq and Ribécourt-Dreslincourt.

When are the trucks going?
The movement of trucks between the CSNE worksites will begin this summer and will continue
until the end of the year*.

*Subject to weather conditions and site hazards.

Document

Added July 10, 2023 - Updated March 24, 2025

Truck traffic work info this summer - Montmacq / Ribécourt-Dreslincourt

Document

Added August 16, 2023 - Updated August 16, 2023

Info work 16/08/23 - Increased truck traffic / Montmacq

JUNE 26 – 30, 2023: DRILLING OF METALLIC TUBES - MONTMACQ

What is it about ?

As part of the work to rescinde the Oise, a temporary bridge has been put in place over the Matz to allow construction machinery to cross this watercourse, flowing from the Oise river. To make the foundations and supports for this bridge, metal tubes of about 15 meters must be driven into the ground. 

How long does this work take?

The beating of the metal tubes will be carried out discontinuously over a period of 2 to 3 days between June 26 and 30, 2023*, during the usual hours of the site, from Monday to Friday between 8 a.m. and 18 p.m.

How are metal tubes installed?

As with sheet pile driving, the tubes will be driven into the ground using a pneumatic hammer or vibratory hammer type machine.

 

* Subject to weather conditions and site hazards.

Document

Added June 19, 2023 - Updated March 24, 2025

Info Works 19/06/23 driving metal tubes - Montmacq

ACTIVITY ON THE SITE OUTSIDE WEEKDAYS - MONTMACQ / CAMBRONNE-LÈS-RIBÉCOURT

Why does work take place outside working days?

As part of the work to rescinde the Oise and the construction of the Siphon du Moulinet, certain operations require the maintenance of activity on the site over extended periods or are dependent on weather conditions. For these reasons, the company in charge of the works sometimes needs to intervene on Saturdays or public holidays.

What days and work are involved?

Thursday, May 18, 2023*: earthworks for the rescindement of the Oise and digging of the Siphon du Moulinet.

The Saturdays June 3 and 17, 2023*: digging works for the Siphon du Moulinet.

In the coming months, other operations will take place on the site, between Montmacq and Cambronne-lès-Ribécourt, on Saturdays or on public holidays. We will inform you when these works will have an impact on traffic or the generation of noise.

* Subject to weather conditions and site hazards.

Document

Added May 15, 2023 - Updated March 24, 2025

Info Works 15/05/23 - Activity on the site outside working days

APRIL 26 - MAY 3: PILE DRIVING - MONTMACQ

What is it about ? 

As part of the construction of a temporary bridge over the Oise, allowing the companies in charge of the work to access certain areas of the site, piles will be driven from time to time in order to build the foundations and supports of the bridge.

What is the duration of these works*?

Pile driving will take place punctually from April 26 to May 03, 2023 from Monday to Saturday between 8 a.m. and 18 p.m.

* Subject to weather conditions and site hazards.

Document

Added April 26, 2023 - Updated March 24, 2025

Info Works 26/04/23 pile driving - Montmacq

MARCH 31 - MAY 26: EXTENDED REEL SIPHON WORK HOURS EXPANDED

What changes and for how long?

The hours of the construction site must finally remain extended from 6AM to 22PM over the periods of March 31 to May 26, 2023* (Saturday included but not Sunday).

*Subject to weather conditions and site hazards.

Document

Added March 29, 2023 - Updated March 24, 2025

Info Works 31/03/23 Siphon du Moulinet - extension of the extended working hours

MARCH 22: BEGINNING OF WORK ON THE "RD 40 BIS" BRIDGE - PIMPREZ

What works have been carried out?

Construction work on the "RD 40 bis" bridge began with the installation of sheet piles to support and reinforce the ground of the service road which will be created after the construction of the bridge abutments.

How are they going?

This stage consists of driving large steel sections into the ground by vibro-driving and then, in a second step, carrying out the piling to finalize their anchoring in their ground. If the vibratory driving is hardly perceptible, the driving of the sheet piles generates noise during its realization. It is however necessary to finalize the sinking of the sheet piles.

What is the duration* of the work?

The first sheet pile driving tests took place from March 22 and operations will continue until the end of March.

The work will take place from Monday to Friday from 8 a.m. to 18 p.m.

* Under adverse weather conditions and site hazards

Document

Added March 24, 2023 - Updated March 24, 2025

Info Works 24/03/23 "RD 40 bis" bridge - Pimprez

MARCH 13 - APRIL 22: MODIFICATION OF THE HOURLY AMPLITUDE OF THE REEL SIPHON WORKS

What changes and for how long?

Construction hours will be extended from 6AM to 22PM over the following periods*:

  • Du March 13 to March 31, 2023 (Saturday included but not Sunday),
  • Du April 17 to April 28, 2023 (Saturday included but not Sunday).

Why are the hours extended?

The creation of this work consists in digging a micro tunnel (with a diameter of approximately 1m), passing under the future Canal Seine-Nord Europe to allow the watercourse of the Moulinet to join the new bed of the Oise. The micro-tunnelling machine – the machine used to build the tunnel – needs to operate over extended hours to progress because, in addition to digging the ground, it also lays the walls of the tunnel, thus making it possible to stabilize it. These operations must be carried out over long amplitudes.

*Subject to weather conditions and site hazards.

Document

Added March 10, 2023 - Updated March 24, 2025

Info Works 13/03/23 Siphon du Moulinet

NOVEMBER 28 - DECEMBER 2, 2022: CUTTING THE RD 66 BETWEEN MONTMACQ AND CAMBRONNE​

What is it about ?

Work to rescinde the Oise along the RD66 began this summer and is entering a phase which requires the temporary interruption of all traffic between Montmacq and Cambronne-lès-Ribécourt to guarantee the safety of users and personnel working on the building site.

When will the county be cut off?

The RD 66 will be closed days and nights, from Monday November 28 to Friday December 2, 2022 included*. The companies managed to limit the road closure to just 1 week instead of the 4 announced. The bridges crossing the Oise and the side canal to the Oise will be inaccessible over the period.

* Subject to weather conditions and site hazards.

Document

Added November 17, 2022 - Updated March 24, 2025

Info Works 21/11/22 Montmacq / Cambronne

BEAURAINS-LÈS-NOYON: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

The work essentially consists of exploiting the poplar plantation and replanting alluvial afforestation. Ponds will also be created.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Trucks to evacuate excavated soil and cut wood will circulate over the period. Alternating traffic will be put in place from time to time. The other interventions (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated March 19, 2025

Info works 22/08/22 Beaurains-lès-Noyon

PIMPREZ – CHIRY-OURSCAMP: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

Shallow planting and earthworks are carried out, in particular to create ponds and restore backwaters favorable to biodiversity.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Excavated earth evacuation trucks will circulate over the period. The other operations (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated March 19, 2025

Works info 22/08/22 Pimprez / Chiry-Ourscamp

MORLINCOURT: ENVIRONMENTAL COMPENSATION WORK FROM SEPTEMBER 1 TO NOVEMBER 31, 2022

What works are carried out?

Environmental planting and shallow earthworks are being carried out to the east of the village, along the Oise side canal, in particular to restore wetlands and create ponds favorable to biodiversity.

When and how does this work take place?

The main works are planned between September 1 and November 31, 2022*. Excavated earth evacuation trucks will circulate over the period. Alternating traffic will be put in place from time to time. The other interventions (planting, sowing, mowing, etc.) may continue until mid-March 2023.

* Subject to weather conditions and site hazards.

Document

Added August 31, 2022 - Updated March 19, 2025

Info works 22/08/22 Morlincourt

CAMBRONNE-LÈS-RIBÉCOURT: DEMOLITION OF BUILDINGS IN MAY 2022

What works are carried out?

Four houses in Cambronne-lès-Ribécourt must be destroyed to allow the construction of a new bridge over the side canal to the Oise. At the same time, network rerouting operations (water, electricity, telephone, etc.) are carried out by concessionaires.

When and how does this work take place?

Work will begin between May 2 and May 6 and will last approximately 5 weeks*. They will take place from Monday to Friday, between 8 a.m. and 18 p.m. They will generate noise and unusual machinery traffic. For everyone's safety, the bottom of rue du Bac may occasionally be closed to road traffic during these 5 weeks.

*subject to weather conditions and site hazards.

Edit 19/05: the demolition work will start from June 1, 2022. Indeed, the visit of the ecologist highlighted the presence of birds whose breeding period requires delaying the work.

Document

Added April 4, 2022 - Updated March 24, 2025

WORKS INFO 04/04/22 CAMBRONNE

Demolition of buildings

RIBÉCOURT / PIMPREZ: SHEET PILE INSTALLATION WORK BETWEEN FEBRUARY AND APRIL 2022

What works are carried out?

Construction of the Canal quays at Ribécourt-Dreslincourt and Pimprez is continuing and sheet pile driving will take place on both sites. This stage consists of driving large steel sections into the ground intended to retain the earth and serve as a support for the quay. The sheet pile wall also contributes to sealing the walls of the Canal.

What is the duration* of the work?

The driving of sheet piles on the 200 meters of linear quay at Pimprez and the 150 meters of quay at Ribécourt-Dreslincourt is planned between mid-February and mid-April 2022. Work will take place on weekdays and during the day only, Monday to Friday, between 8 a.m. and 18 p.m.

*subject to weather conditions and site hazards.

Edit 25/02: the sheet piles are being delivered, and driving will start on March 8.

Edit 12/04: after the first successful vibrosinking operations, the rest of the work requires the initially announced sheet pile driving, which will continue until the end of April.

 

Document

Added February 6, 2022 - Updated March 24, 2025

WORKS INFO 06/02/22 RIBÉCOURT / PIMPREZ

Installation of sheet piles

MONTMACQ: SHEET PILE DRIVING TESTS IN JULY 2021

What is it about ?

The watertight walls of water retaining structures are made up of large steel sections, called sheet piling, interlocked edge to edge. Driving refers to the step that consists of driving the sheet piles into the ground.

When and where does this work take place?

The work will take place in Montmacq during the day, Monday to Friday, over 2 to 4 weeks during July 2021* (behind the ADP ponds).

*subject to weather conditions and site hazards.

Document

Added June 28, 2021 - Updated March 24, 2025

WORK INFO 28/06/21 MONTMACQ

Sheet pile driving tests

RIBÉCOURT / CAMBRONNE: SHEET PILE DRIVING TESTS IN JULY 2021

What is it about ?

The watertight walls of water retaining structures are made up of large steel sections, called sheet piling, interlocked edge to edge. Driving refers to the step that consists of driving the sheet piles into the ground.

When and where does this work take place?

The work will take place during the day, Monday to Friday, over 2 to 4 weeks during July 2021* (at the “Quai SECO”, along the towpath).

*subject to weather conditions and site hazards

Document

Added June 28, 2021 - Updated March 24, 2025

WORKS INFO 28/06/21 RIBÉCOURT / CAMBRONNE

Sheet pile driving tests