New stage in the construction of the lock in sector 1

Since the beginning of December 2025, the construction of the diaphragm walls has started on the Montmacq lock construction site –
Cambronne-lès-Ribécourt. What do these works consist of, how are they carried out? Explanations.

A first structuring phase

The construction of the Montmacq – Cambronne-lès-Ribécourt lock begins with the creation of a watertight enclosure, made up of concrete walls called diaphragm walls.

Diaphragm walls are constructed by excavating trenches up to 20 meters deep using a mechanical excavator. These trenches are stabilized with a mixture of water and bentonite clay, which prevents groundwater infiltration and soil erosion. A reinforcing cage is then inserted before concrete is poured into it. Being denser than the bentonite, the concrete displaces the bentonite, filling the trench and thus forming the wall.

The walls of the lock chamber are built first, then those of the upstream and downstream heads of the lock and finally, of the pumping station (see photo below).

Diaphragm walls in pictures

Construction steps in video

The book in figures

  • 6,41 meters drop height
  • Airlock 195 meters long and 12,5 meters wide
  • Diaphragm walls 20 meters deep
  • 200 people were mobilized at the peak of the construction project.